After the 15% advance payment to the Italian company the repairs to the dam in Honduras will begin in December and will take two years.
After countless delays, repair of the hydroelectric finally will finally have free reign, after the award in May and the signing of the contract in August to repair cracks and the slope in the tunnels.
The offers submitted by three foreign companies for repairing cracks in the dam range from between $33.3 million and $34.3 million.
The Swiss-Venezuelan consortium Rodio Swissboring-Trevi Cimentaciones, the Italian Astaldi S.P.A. , and the Mexican Tecnosuelo, SA de CV are the three companies who submitted financial bids for the work.
The same companies that had participated in two failed international tenders have submitted two bids for the repair of the El Cajon dam.
The Consortium MOS, made up of the Swiss company Rodio Swissborring and the Venezuelan Trevi Cimentaciones, the Italian Astaldi S.P.A., China's Sinohydro Corporation Limited and the Mexican Tecnosuelo S.A. de C.V. , submitted bids in the private tender conducted by Empresa Nacional de Energía Eléctrica (ENEE) for repairing cracks in the El Cajon hydroelectric station.
After the failure of two tenders for the repair of cracks in El Cajon, the contract for approximately $30 million will be awarded directly.
Empresa Nacional de Energía Eléctrica (ENEE) has $30 million available to carry out the work."We have to look at the parameters and see if the law allows us to negotiate a contract directly. When you do not have any bidders, you take the ones that are there and follow the path with them directly," said Emil Hawitt, manager of the company.
The second tender for repairing the cracks in the El Cajon hydroelectric station has been declared void because bidders lacked the required technical ability.
This is the second time that the tender to repair the leaks in the curtain and the rocky walls of the hydroelectric station Francisco Morazán, better known as "El Cajon", has been declared void by Empresa Nacional de Energía Eléctrica (ENEE).
The National Electricity Company of Honduras is putting out to tender maintenance of underground construction works at the hydroelectric station General Francisco Morazán.
The objective of the international tender is to hire out special maintenance works on the hydroelectric station Francisco Morazán.
The administration of the Francisco Morazán reservoir announced that next March a tender will be re-launched for a project to repair cracks in the El Cajon hydroelectric dam.
Cracks in the Francisco Morazán hydroelectric station are causing state losses of over $2 million a year because of the water that is lost instead of going to the engine room.
The contract to repair the leaks in the power plant "El Cajon", which favoured the company Rodio Swissboring Centroamérica, which bid $39.5 million, has been declared unsuccessful, said the manager of the National Electricity Company (ENEE), Roberto Cardona .
The works to be completed include repair of leaks in the "El Cajon" dam that occurred after the earthquake measuring 7.3 on the Richter scale on 28th May 2009.
The ICE has invited bids for a $1.5 million feasibility study for modernizing the Arenal hydroelectric plant.
The Arenal hydroelectric plant is one of the main plants in the National Electricity System (SEN), not only for its generation capacity but also because of its ability to regulate the system. It has an installed capacity of 157,398 kW and ranks third in generating capacity of all plants in the SEN and contributes on average about 641 GWh per year.
In September, the regulator will start the bidding process to hire a company to undertake repairs and maintenance.
The cost of repairs according to information from the National Electricity Company (ENEE), is about $20 million.
Sub technical manager of ENEE, Leonardo Deras told Latribuna.hn that domestic and foreign experts have agreed on the urgency of initiating repairs and maintenance.
The bidding rules to repair hydroelectric power plant “Francisco Morazán”, also known as “El Cajón”, are ready for publication.
Roberto Martínez Lozano, head of the National Electric Energy Corporation (ENEE), explained that they will invite domestic and foreign companies to participate in the project as soon as possible.
The government will invite companies to bid for repairing cracks at “El Cajón” hydroelectric power plant, also known as “Francisco Morazán”.
Manuel Palma, executive director of the plant, commented they will publish the bidding rules in the next days and that works should begin on June.
“Ana María Castro, president of the Association of Civil Engineers of Honduras, requested authorities to include her organization as the social auditor of the project”, reported Laprensa.hn.
O4Bi is a system that allows to control and manage what a company needs: the complete process of development of works, accounts receivable, treasury, banks, sales and accounting.
O4Bi is a very robust system that allows to control and...
Recognized Brazilian company of backhoe loaders, telescopic, articulated and other types of cranes looking for companies interested in representing the brand and distributing their machinery in Central America and Mexico. The company manufactures and sells telescopic,...