The Oil Dock at Moin

The Costa Rican Oil Refinery has given the order to start works to the consortium ICA-MECO (ICA Ingenieros Civiles Asociados de C.V-Constructora Meco S.A).

Tuesday, May 22, 2012

A statement from the Costa Rican Oil Refinery (RECOPE) reads:

On May 15 the order was given for the proposed expansion of the Atlantic port terminal, awarded to the consortium ICA-MECO (ICA Ingenieros Civiles Asociados de C.V-Constructora Meco S.A).

The awarded company will be responsible for the review and adjustment of the basic and detailed engineering provided by the Costa Rican Oil Refinery (RECOPE SA), the supply of materials and equipment, construction, commissioning and transfer of technology for the operation of the new dock.

According to the schedule the work is expected to be completed during the months of June / July 2014. In total, construction will last for 26 months and will cost $96 million. The project involves the construction of a pier with mooring dolphins, which can safely download products that the country needs, such as oil, gasoline, diesel and A-1 jet fuel. The port work is an extension of the current oil dock, so it will be necessary to dredge at least 1.9 million cubic meters of material, extending the northern breakwater by 200 meters and building four piers with mooring dolphins (two in the sea two on land) and a loading dock.

In addition, the project involves the construction of all the systems needed to provide security and operational efficiency, such as navigational aids, pipelines for oil transfer, fire fighting, automation and control, among other things. Some direct benefits that the development of new oil terminal will bring are the incorporation of new technologies making port operations more efficient as they will be able to operate 24 hours a day and also the capacity of vessels for the new facilities will be expanded enabling the ability to receive ships of 80,000 deadweight tons (560,000 barrels).

¿Busca soluciones de inteligencia comercial para su empresa?



More on this topic

Works on Oil Dock in Moín Still Paralyzed

July 2017

There is still no certainty as to when construction of the dock will resume, rather than being ready by the middle of this year, it will be delayed until at least January 2018.

Initial plans were that Recope's oil dock, which will allow larger vessels to dock, would be ready by the middle of this year, but it is now estimated that it could be completed in early January next year, due to problems that arose during the construction process, which is being run by the consortium ICA-MECO.

Contract Endorsed for Oil Dock in Moin

March 2012

The green light has been given to a contract between the Costa Rican Oil Refinery (Recope) and the ICA-MECO consortium for the works which will cost $97 million.

The Controller General of the Republic (CGR) has endorsed a contract between the Costa Rican Oil Refinery (Recope) and the consortium ICA-MECO, a case which has been pending since 1998.

Controller Confirms Award of Oil Terminal Works

December 2011

The Controller of the Republic of Costa Rica has confirmed the award of the works on the oil terminal to the consortium ICA-MECO.

The regulator dismissed appeals filed against the award on the grounds that they lacked merit.

"The tender promoted by the Costa Rican Oil Refinery (Recope) includes the construction of a Dukes quay berth, via which products that the country needs, such as gasoline, diesel and oil can be unloaded.

ICA-MECO is Awarded Oil Dock in Costa Rica

August 2011

The consortium will have 26 months to develop the oil dock project at Moin, at a cost of $96 million.

The Costa Rican Petroleum Refinery has awarded the construction and commissioning of the new oil dock to the consortium ICA - MECO, made up of the companies Ingenieros Civiles Asociados de CV and Constructora Meco S.A.