Empresa de Transmision Electrica bids the analysis, preliminary studies and consulting services for the preparation of the environmental impact study of the project called Chiriquí Grande-Panamá III, 500 Kv operating at 230 Kv.
Thursday, April 29, 2021
Panama Government Purchase 2021-2-78-0-04-LV-013730:
"The commitment includes without limitation: equipment, products, accessories, suitable staff registered as Consultant and Environmental Auditor with the Ministry of Environment (registrations in force for the term of the Consultancy) and auxiliary (field staff).
This work team shall have the economic, operational and technical capacity, equipment, technology, materials and experience to guarantee compliance with the assigned responsibilities, and shall work closely with the Contracting Entity.
The Consultant for the Preparation of the Environmental Impact Study must have a work team made up of at least two (2) work fronts integrated by the following professionals: one (1) General Coordinator, four (4) Area Coordinators (Physical, Biological, Socioeconomic and Occupational Health and Safety - OSH), two (2) Geographers, two (2) Geologists, two (2) Soil Scientist/Podologists, two (2) Hydrologists, two (2) Cartographers/GIS, two (2) Topographers, six (6) OSH Specialists, twelve (12) Field Assistants, two (2) Forest Engineers, two (2) Botanists, two (2) Ornithologists, two (2) Herpetologists, two (2) Mastozoologist, two (2) Ichthyologist, two (2) Chiroptera, two (2) Natural Resources Specialist, two (2) Wildlife Specialist, two (2) Zoologists, two (2) Sociologist, two (2) Anthropologist/Archaeologist and two (2) Community Development Specialist and one (1) Economist".
¿Le interesan las licitaciones en Centroamérica y República Dominicana? Reciba a diario alertas sobre las compras de gobierno del sector de su interés.
SOLICITE UNA COTIZACIÓN DEL SERVICIO
Your message has been sent. We will contact you shortly.
Plans are underway to build a 9.6-kilometer-long transmission line between the substations of the future GTPP plant and that of Sabanitas, located in the province of Colón, Panama.
The company Martano Inc submitted an Environmental Impact Study (EIA) to build a 9.6-kilometer-long transmission line from the site of the future substation in the Río Alejandro Energetic Park project to the Sabanitas substation, owned by Empresa de Transmisión S.A.
Adding a capacitor bank and installing a transmission line are part of the energy projects for which environmental impact studies were presented in November 2015.
The report "Construction Projects in Panama - November 2016", prepared by the Business Intelligence unit at CentralAmericaData.com, provides a detailed list of major the construction projects for which environmental impact assessment (EIA) studies were presented in November to the Ministry of Environment in Panama.
×
2321Government Procurement Opportunities in the region