Empresa Nacional de Energía Eléctrica de Honduras is putting out to tender the provision of general services at the Francisco Morazán hydroelectric plant.
"To participate in the tender for the provision of general services at the General Francisco Morazán Hydroelectric Power Plant (El Cajón), the bidders must acquire the tender conditions from the institution's site building.
All offers must be accompanied by a guarantee of maintenance of the offer for an equivalent of at least 2% of the total value of their offer."
The deadline for receipt of bids is March 19, 2018.
The Rio Lempa Hydroelectric Executive Commission is tendering the supply of goods and services for preventive maintenance every 10 years for unit 2 of the 15 de Septiembre hydroelectric plant.
El Salvador Government Purchase CEL-LP 06/20:
"It will be considered that for the supply of goods and contracting of the requested services, they are integral; that is to say, after the provision of the requested supervision services, the systems of turbine speed regulator, thrust bearing lifting, upper, intermediate and lower bushings of distributor blades, distribution valves for impeller blades and distributor blades and carbon seal, will be fully functional and will operate in a satisfactory manner for CEL.
The National Institute of Electrification of Guatemala tenders the supply, installation and commissioning of hydrating equipment for the Jurúm Marinalá hydroelectric plant.
Guatemala Government Purchase 10627634:
"The new cistern must be for water, with a minimum capacity of 80 cubic meters, leaving a differential from the level to the roof of the tank of 20 to 30 centimeters.
The National Electrification Institute of Guatemala is putting out to tender the supply and commissioning of boards in the auxiliary services distribution system of the Jurún Marinalá plant.
Guatemala Government Purchase 9035001:
"The Contractor must consider an analysis of the calculation of the different electrical circuits in order to determine the correct protection, in order to optimize the updating of the plant's distribution boards, in which intelligent link technology is implemented, to facilitate real-time monitoring of each of the main and secondary circuits of the different boards in the direct current and alternating current auxiliary servicesdistribution system in the machine house.
The National Electrification Institute in Guatemala (Instituto Nacional de Electrificación de Guatemala) is putting out to tender dam security tests at the Chixoy hydroelectric plant.
Guatemala Government Purchase 7531036:
"The structures that comprise the security test are the following:
×
 close (x)
Receive more news about Electrical equipment and supplies
Suscribe FOR FREE to CentralAmericaDATA EXPRESS.
The most important news of Central America, every day.
Mexican manufacturer of office furniture seeks importers and distributors interested in dealing their products in Central America.
PM Steele is a 100% Mexican company, with more than 67...