Tender: Electricity Works for $10 million

The Electricity Transmission Company of Panama is putting out to tender the supply, assembly and commissioning of the Burunga substation.

Tuesday, July 4, 2017

Panama Government Purchase 2017-2-78-0-15-LP-008787:

"The contract includes the implementation of the project "Supply, Assembly, Commissioning, Commissioning and Civil Works for the Burunga Substation", which consists of the following sub-projects:

-Construction of the new automated substation Burunga 230kV in switch and half format. Two (2) circuit breakers with three (3) interruptors, for the sectioning of the 230 KV El Coco - Panamá II line (230-12 and 230-13). One (1) breaker with three (3) switches for the connection of the two (2) autotransformers 230 / 34.5 KV, 100 MVA, owned by EDEMET.

-Adaptations needed in the El Coco and Panama II substations to incorporate the Burunga Substation into the National Interconnected System.

-Sectionalization of the existing transmission line of 230-12 / 13 kV. El Coco - Panamá II (Circuits 230-12 and 230-13), through underground cables."

Reference value:  $10.000.000 

The deadline for receipt of bids is August 17, 2017.

See Tender

Are you interested in tenders in the region?

Receive daily alerts about major purchases by governments in Central America.

Find out more:









this site is protected by reCAPTCHA and Google's privacy policy and terms of service.
Need assistance? Contact us
(506) 4001-6423


More on this topic

Tender for $26 Million in Electrical Works

December 2018

The works of the Transmission Line 230 KV, Panama II - Chepo, circuit repowering, supply, assembly, commissioning, setting in service and civil works are tendered.

Panama Government Purchase 2018-2-78-0-08-LV-010849:

"The object of the contract includes the execution of:

Tender: Electricity Works for $81 million

August 2016

Panama is inviting bids for supply and services for the repowering of the Panama II-Chepo Line and the new LT Chepo -Meteti, 230kV and associated substations.

Panama Government Purchase 2016-2-78-0-08-LP-007309:

"This contract includes the completion of the project called "Transmission Line Panama II-Chepo-Metetí -230 KV "consisting of:

Tender: Electrical Equipment for $34 million

September 2015

The Electricity Transmission Company of Panama is putting out to tender a supply of power autotransformers, equipment, materials and services for static reactive power compensators.

Panama Government Purchase 2015-2-78-0-99-LP-006214:

"Supply of equipment, materials and reactive static power compensator services (SVC / STATCOM) in the substations Panama II and Llano Sanchez, 230 kV."

Panama: Tender for Works on Electric Substations for $4.6 million

August 2011

The Electricity Transmission Company has put out a tender for construction works on Substation Chorrera and Substation Sáchez Llano.

The contract includes the construction of extensions to the 230kV and 34KV yards at Substation Chorrera and the 230kV and 115kV yards at Substation Sáchez Llano.

 close (x)

Receive more news about Electrical equipment and supplies

Suscribe FOR FREE to CentralAmericaDATA EXPRESS.
The most important news of Central America, every day.

Type in your e-mail address:

* Al suscribirse, estará aceptando los terminos y condiciones


Stock Indexes

(Apr 6)
Dow Jones
-5.60%
S&P 500
-5.10%
Nasdaq
-5.64%

Commodities

(Jan 18)
Brent Crude Oil
86.740
Coffee "C"
239.55
Gold
1,821
Silver
23.060