Route to Limón Would Be Ready in March 2021Due to delays caused by situations beyond the control of China Engineering Company, the Costa Rican authorities agreed to postpone by 174 days the delivery of the work to expand Route 32.Monday, December 2, 2019
Initially the China Engineering Company (CHEC), asked the National Road Council (Conavi) for an extension of 400 days to deliver the extension of 107 kilometers, which connects the crossing to Rio Frio with the center of Limon, however, the authorities only agreed to delay for 174 days, therefore, the work would be delivered no later than March 2021. Source: Nacion.com Are you interested in construction projects in Central America?Keep track of all the projects that will be developed in the region through our online interactive Construction Platform. More info here Route to Limon: New Delay ExpectedMarch 2020 Due to the health alert facing Costa Rica, the China Harbor Engineering Company decided to lay off 180 employees working on the Route 32 expansion project, which has already fallen behind on previous occasions. Costa Rica: Road Construction to Limón DelayedJuly 2017 The Chinese company in charge of the project will start construction work in the second half of 2018, and not in September of this year, as originally planned. Costa Rica: Deadline to Sign $395 million Chinese Loan ExtendedJune 2014 China Harbour Engineering Company has accepted a request by the Solis administration to extend the signing a loan to be used for the extension of the road going from San José to the Caribbean. Alternative to $465 million Road Contract with ChinaMarch 2014 Five Costa Rican construction companies have submitted a joint proposal to take over the expansion to four lanes of 107 miles of kilometers to the Caribbean.
×
|
![]()
|