Private Tender For Repairing Hydropower Station in Honduras

The same companies that had participated in two failed international tenders have submitted two bids for the repair of the El Cajon dam.

Thursday, December 12, 2013

The Consortium MOS, made up of the Swiss company Rodio Swissborring and the Venezuelan Trevi Cimentaciones, the Italian Astaldi S.P.A., China's Sinohydro Corporation Limited and the Mexican Tecnosuelo S.A. de C.V. , submitted bids in the private tender conducted by Empresa Nacional de Energía Eléctrica (ENEE) for repairing cracks in the El Cajon hydroelectric station.

The previous two tenders were declared unsuccessful because of an overvaluation of bids and because companies did not establish their expertise in this type of work. However, this time amendments have been made and credentials certified through a legal document stating that they are trained to perform the repairs.

The reception of bids was scheduled for next week, but the ENEE brought forward the date for bidders to submit their proposals. Although no explanation was given it is presumed that this was because there is a lot of interest in holding the tender before the end of the current government, because if it is left to the next administration the process could be lengthened.



More on this topic

Honduras Awards for Repair Work at El Cajon Hydroelectric Station

May 2014

With an offer of $31.8 million, the Italian Astaldi emerged as the winner in the tender to repair cracks in the El Cajon hydroelectric dam.

From a press release issued by the National Energy Electricity Company of Honduras :

The National Electricity Company, communicates the following for national public opinion :

Honduras: Three Offers for El Cajon Hydroelectric Station

April 2014

The offers submitted by three foreign companies for repairing cracks in the dam range from between $33.3 million and $34.3 million.

The Swiss-Venezuelan consortium Rodio Swissboring-Trevi Cimentaciones, the Italian Astaldi S.P.A. , and the Mexican Tecnosuelo, SA de CV are the three companies who submitted financial bids for the work.

Direct Contract for Works on Hydro Station

October 2013

After the failure of two tenders for the repair of cracks in El Cajon, the contract for approximately $30 million will be awarded directly.

Empresa Nacional de Energía Eléctrica (ENEE) has $30 million available to carry out the work."We have to look at the parameters and see if the law allows us to negotiate a contract directly.

Tender for the El Cajon Hydroelectric Station is Unsuccessful

August 2012

The National Electricity Company of Honduras announced that there will be another international tender for repairing leaks at the hydroelectric plant.

The contract to repair the leaks in the power plant "El Cajon", which favoured the company Rodio Swissboring Centroamérica, which bid $39.5 million, has been declared unsuccessful, said the manager of the National Electricity Company (ENEE), Roberto Cardona .

 close (x)

Receive more news about Energy

Suscribe FOR FREE to CentralAmericaDATA EXPRESS.
The most important news of Central America, every day.

Type in your e-mail address:

* Al suscribirse, estará aceptando los terminos y condiciones


Tailor made software for construction companies

O4Bi is a system that allows to control and manage what a company needs: the complete process of development of works, accounts receivable, treasury, banks, sales and accounting.
O4Bi is a very robust system that allows to control and...

Stock Indexes

(Apr 6)
Dow Jones
-5.60%
S&P 500
-5.10%
Nasdaq
-5.64%

Commodities

(Jan 21)
Brent Crude Oil
55.920
Coffee "C"
128.75
Gold
1,869
Silver
25.975