Opening of Moin Mega Port Delayed

Due to several constructive defects, the Dutch company APM Terminals anticipates that the opening of the container terminal will take place in June 2018 and not in January, as originally planned.

Tuesday, June 27, 2017

According to authorities of the concessionaire, among the inconveniences that have occurred in the process of constructing the port terminal are poor compaction of the surface of the 40 hectare artificial island, and damages in 20 meters of the breakwater, among other things. APM Terminals estimates that the work will be completed in June 2018, and not on January 18, as indicated in the contract. 

Nacion.com reports that "...The agreement establishes a $2,000 penalty for each day of delay in opening the port. The maximum amount for this default is $200,000. Aside from this punishment, for every day of delay in construction the State can charge a $2,000 fine."

Kenneth Waugh, general manager of the company, "... considered that the obstacles they face will give the National Road Council (Conavi) time to complete route 257 that connects the road to Limón with the megaport, which is also reporting delays."

More on this topic

Panama: Backwards Step for Mega Port in Isla Larga Remo

March 2016

The government has rejected the environmental study run by the Martinelli administration for the construction of the terminal and has put the project on hold.

The multipurpose wharf project Puerto Verde Panama Atlantico, which involved the sale of Isla Largo Remo and the construction of a mega terminal for handling containers from super post panamax ships, has been canceled.

APM Terminals To Start Work in January 2015

December 2014

In Costa Rica an order has been given to start work no later than January 19, and according to APM Terminals, they will start with construction of the breakwater and dredging of the access channel.

According to the instructions given by the National Tender Board, the construction of a port terminal in Moin should be starting in exactly one month. In order to get started with the first works, 600 workers will need to be hired.

Court Clears Way for New Mega Port

October 2014

A constitutional court has rejected appeals by port unionists and announced that the construction of the Container Terminal at Moin will begin in early 2015.

From a statement issued by APM Terminals:

San José, Costa Rica, October 9. The Supreme Court has ruled in favor of the Costa Rican Government and APM Termináis in an appeal filed by the port workers unión against the 33-year concession contract for the new Moin Container Terminal (TCM) in Limón on the Caribbean coast of Costa Rica.

Does Costa Rica Really Want a New Port?

April 2014

There are so many obstacles faced by the project being run by Dutch APM Terminals that it begs the question as to whether the Costa Rican government really wants it to happen.

Since it was awarded construction of the New Mega Port for specialized container ships in Moin, the Dutch company APM Terminals has faced dozens of lawsuits and other legal measures in the courts, which has maintained continuous doubts about the realization of the project.

 close (x)

Receive more news about Infrastructure & Construction

Suscribe FOR FREE to CentralAmericaDATA EXPRESS.
The most important news of Central America, every day.

Type in your e-mail address:

* Al suscribirse, estará aceptando los terminos y condiciones


Tailor made software for construction companies

O4Bi is a system that allows to control and manage what a company needs: the complete process of development of works, accounts receivable, treasury, banks, sales and accounting.
O4Bi is a very robust system that allows to control and...

Stock Indexes

(Apr 6)
Dow Jones
-5.60%
S&P 500
-5.10%
Nasdaq
-5.64%

Commodities

(Oct 15)
Brent Crude Oil
80.41
Coffee "C"
122.95
Gold
1,228
Silver
14.676