New tender for the Children's Hospital

After several problems occurred in the previous processes, the Ministry of Health of Panama announced a new tender to build and equip the new Children's Hospital.

Wednesday, January 9, 2019

The new public procurement process must be carried out because the General Directorate of Public Contracting (DGCP) annulled the reports drafted by the commission evaluating companies interested in participating in September and November 2018.

According to the new tender published on January 8 of this year the reference value is $559 million and the deadline for receipt of tenders is February 21, 2019.

The tender consists of the construction, equipment and corrective and preventive maintenance of the New Children's Hospital, the maternity hospital of Santo Tomás and adjacent areas, restoration of gardens and remodeling of the Abeja Building.

See tender.

Do you need more information about your business sector?

Request more information:








this site is protected by reCAPTCHA and Google's privacy policy and terms of service.
Need assistance? Contact us
(506) 4001-6423


More on this topic

Two Proposals for Hospital Work

April 2019

In Panama, the CAMCE Hospital del Niño and Acciona Construcción, S.A. Consortiums presented their proposals to build and equip the new Hospital del Niño.

During the event held on April 15, Consorcio CAMCE Hospital del Niño presented a $613 million bid and Consorcio Acciona Construcción, S.A.'s bid totaled $614 million.

Children's Hospital to be Re-tendered

December 2018

As the evaluation reports of the five consortia participating in the prequalification were cancelled, the Ministry of Health of Panama will have to launch another tender.

The process for awarding the studies, construction, equipment and preventive and corrective maintenance of the New Children's Hospital has suffered another setback, since now a new tender will have to be called.

Reevaluating Offers for Children's Hospital

October 2018

In Panama, the report of the Verification Commission, which in September evaluated the proposals of the companies interested in the work and ordered a new analysis, was partially cancelled.

In September, it was reported that the General Directorate of Public Contracting decided to admit the Complaint Action presented by the representative of the China Camc Engineering Company, against the evaluation report of the act of "Prequalification for the studies, construction, equipment and maintenance of the new Children's Hospital, the Maternity Hospital of Santo Tomas, and adjacent areas, restoration of the gardens and renovation of the Abeja building."

Companies to be Prequalified to Build Hospital del Niño

February 2018

The Panamanian government has decided to submit to a prequalification process all companies interested in the tender to build and equip the new medical center.

The controversial tender, which for several reasons has been delayed for several years, will now be run using a pre-qualification process. See: "Hospital Tender Delayed".

 close (x)

Receive more news about Infrastructure & Construction

Suscribe FOR FREE to CentralAmericaDATA EXPRESS.
The most important news of Central America, every day.

Type in your e-mail address:

* Al suscribirse, estará aceptando los terminos y condiciones


Looking for Importers and distributors of furniture

Mexican manufacturer of office furniture seeks importers and distributors interested in dealing their products in Central America.
PM Steele is a 100% Mexican company, with more than 67...

Stock Indexes

(Apr 6)
Dow Jones
-5.60%
S&P 500
-5.10%
Nasdaq
-5.64%

Commodities

(Oct 23)
Brent Crude Oil
41.99
Coffee "C"
108.05
Gold
1,901
Silver
24.69