New Airport in Guatemala City Questioned

One of the projects which aroused the most interest from foreign investors in the recent Investment Summit has drawn criticism over its design and planning.

Monday, June 10, 2013

The small amount of urban development and the broken terrain in the area of Zone 25 where the Municipality of Guatemala plans to build an international airport have raised questions in the real estate sector.

"We do not see it as suitable. There are more appropriate places, such as the South Coast, land where the topography does not have so many hills," said Carlos Valladares Cerezo, dean of the Faculty of Architecture at the University of San Carlos.

The preliminary studies estimated that construction of the new airport will cost between $500 and $750 million, to which must be added $129 million for a peripheral access road measuring 32 kilometers. "For this route there will be two options: a route on land through the capital city or one following the path of the metropolitan ring road in the department of Guatemala , a district which has not yet clarified its participation", reported Prensalibre.com.

¿Busca soluciones de inteligencia comercial para su empresa?



More on this topic

Panama: Tocumen Airport Will Keep Growing

October 2015

The second terminal under construction will not be enough to meet projected demand by 2020, therefore a third airport expansion is being considered.

The authorities at Tocumen SA have projected that by 2020 the average annual number of passengers who transit through the international airport in Panama City will amount to 20 million and the second terminal, in which they are investing $800 million, will exceed its capacity in 2022.

Guatemala: Preparation for International Airport Opening

January 2014

The start of operations of the international airport in the southeastern part of Guatemala is scheduled for March this year.

The Southern Air Base of Retalhuleu, could be starting operations in March. The airport has the capacity to receive international flights. "Funds for the work were provided by the private sector and the work took about a year."

Remodeling of El Salvador International Airport

April 2012

The infrastructure work and renovation of radar and communications equipment brings the investment to $66 million.

The renovation of the El Salvador International Airport (AIES by its Spanish abbreviations) has entered its first phase, which includes the installation of an elevator, construction of new bleachers, replacement of half the air conditioning systems and changing of 50 % of all toilets.

Tender for South Terminal at Tocumen

January 2012

The airport structure will cost about $400 million and be 50,000 m2 announced Panamanian authorities.

The manager of Tocumen, SA (administrator of the international airport), Juan Carlos Pino, said that the tender for the South Terminal at Tocumen International Airport, Panama will be released in March, and the works are expected to cost $400 million.