More Hydroelectric Stations to be Tendered in El Salvador

It has been announced that the tender documents to choose a company to resume work on the dam El Chaparral, estimated at $291 million, are ready.

Monday, July 13, 2015

Authorities at the Executive Hydroelectric Commission of the Lempa River (CEL) explained that they intend to draw up several contracts to segment work on the project and reduce the total cost. The actual cost of the work remaining to be done is $291 million, "... because CEL is going to move the dike of the dam to prevent slippage on the right side of one of the mountains in the area of ​​the work . "

"... The first two tenders launched (on Thursday 9) are for the hydraulic concrete to be used in construction of the structure of the powerhouse which is part of the hydroelectric project. Both are in the form of co-qualification, ie it is a direct invitation to bidders (without prequalification) and the receipt of bids will take place on August 26, it was reported. "

David Lopez, president of the CEL, told Elsalvador.com that "... 'The tender conditions and all the documentation is ready and available to all interested companies. We are aiming to award contracts to domestic companies because we know there is the expertise here, even though the tender is international due to the regulations for financial entities and transparency of this process'."

¿Busca soluciones de inteligencia comercial para su empresa?

Are you interested in tenders in the region?

Receive daily alerts about major purchases by governments in Central America.

Find out more:









this site is protected by reCAPTCHA and Google's privacy policy and terms of service.
Need assistance? Contact us
(506) 4001-6423


More on this topic

Geological Faults at Chaparral Hydroelectric Plant

January 2011

The problems detected could lead Cel and the Astaldi consortium, responsible for the project, to submit for international arbitration.

The faults which threaten the foundations of the dam were detected after Storm Agatha, halting all works at the site.

The Executive Committee of the Lempa River Hydroelectric Plant (Cel) and the Italian consortium Astaldi, before heading for arbitration, hired an international expert to determine who has the responsibility to cover the additional costs of a possible plant redesign.

Chaparral Hydro Power Plant is 22% Ready

May 2010

17 months after starting construction, hydroelectric power plant “El Chaparral”, located in San Miguel, is 22% ready.

The Hydroelectric Commission for the Lempa River (known as CEL) estimates that the reservoir will begin to be filled on May 2012 and should reach it maximum level in 2013.

El Chaparral Hydro Power Plant in 2013

August 2009

The president of CEL announced that the project is going according to schedule, and will be ready in January 2013.

Nicolás Salume, president of the Executive Hydroelectric Commission of the Lempa River (CEL), added that January 3rd, 2013, is the deadline for the builder to deliver the project.

El Chaparral Dam Project to Initiate in March

February 2009

The BCIE will deliver $31.5 million in March, as an advance for a loan of $162 million, for the start of the construction of the dam El Chaparral.

La Prensa Grafica publishes in its website: "The project will cost $219 million, of which BCIE will contribute 74%, that is to say, $163 million. The remainder $56 million will come from the CEL. The BCIE loan has a time period of 20 years, with an annual interest rate of 6.5%.