Energy Tender Being Prepared in Honduras

The Electricity Regulatory Commission is preparing the documents to tender a supply of firm power, a few months before the current contracts expire.

Tuesday, June 13, 2017

Although the contracts with private suppliers that are about to expire add up to a total of 300 MW, representatives from the Electricity Regulatory Commission (CREE) explained that the tender will not necessarily be for the same amount.

Ricardo Espinoza, president of CREE, explained to Elheraldo.hn that "... the General Law of the Electricity Industry establishes that these contracts can not be renewed and new purchases of energy will be made using an international public tender." 

"... According to projections by the Planning Department of the ENEE, the demand for energy for the period 2018-21 is 272.4 MW, or between 65 and 85 per year."

¿Busca soluciones de inteligencia comercial para su empresa?

Are you interested in tenders in the region?

Receive daily alerts about major purchases by governments in Central America.

Find out more:









this site is protected by reCAPTCHA and Google's privacy policy and terms of service.
Need assistance? Contact us
(506) 4001-6423


More on this topic

Tender for Energy Announced

February 2019

Empresa Eléctrica de Guatemala is preparing three tenders for the energy supply, which will be for one, four and fifteen years.

Empresa Eléctrica de Guatemala, S.A. (EEGSA) reported that the first tender it has planned is a one-year contract from May 2019 for the supply of 71 MW.

Guatemala: Preparations for Tender of 420 MW

January 2017

The electricity distributors Eegsa and Energuate are preparing documents for a tender in the coming months of a supply of 420 MW for a period of 15 years.

Eegsa representatives explained that in one procedure 380 MW will be tendered, in which offers will be accepted with any energy source, but there will be a requirement that generators have at least one year of existence or being constituted.

Guatemala to Tender 380 MW

October 2016

In order to replace the contracts that will soon come to an end electricity distributors are preparing to launch tenders in the coming months for the supply of 380 MW.

It is expected that in the coming months approval will be given by the National Electric Energy Commission (CNEE) for the distributors Empresa Electrica de Guatemala (EEGSA) and Energuate to start the tender processes. In the case of the first entity, the tender will serve to replace a contract with the San Jose plant, which provides 120 MW.

Guatemala: Energy Tender Announced

January 2016

Energuate and Egsa will be holding a briefing on the tender for the supply of electricity for the period May 1st 2016 to April 30th 2020.

Empresa Electrica de Guatemala SA (EEGs) wishes to contract out more than 100 MW annually and the volumes that are to correspond to each distributor are variable, said Carlos Rodas, manager of planning to Prensalibre.com.