Between May 2016 and the same month in 2017, 27 environmental impact studies were presented in the countries of the region for development of energy generation projects.
Friday, July 7, 2017
The interactive platform "Construction in Central America", compiled by the Business Intelligence Unit at CentralAmericaData, includes an up to date list of public and private constructionprojects for which environmental impact studies (EIA) were submitted to the respective institutions in each country.
Panamais the Central American country where the largest investment is concentrated, with an estimated $877 million in energy generation projects, corresponding to 10 environmental impact studies submitted between May 2016 and the same month in 2017.
It is followed by Costa Rica, where 7 EIAs were submitted, with an investment of approximately $254 million.Of the total projects, 5 correspond to wind power generation, one to solar energy generation and the other to the construction of a hydroelectric plant.
In Guatemala, two studies were presented for hydroelectric construction and one for power generation using a steam turbine.The 3 projects add up to an estimated investment of $24 million.
In El Salvador, 5 studies were submitted for installation of solar energy generating systems and one of generation from biogas.Total investment for the projects is approximately $7 million.
CentralAmericaDataprovides information about construction projects planned in all Central American countries, with details such as estimated investment, project times and phases, inputs and equipment that will be required during and after construction, water treatment, parking structure, among others.
Are you interested in construction projects in Central America?
Receive information about our monthly report including a complete list of all the major and most important construction projects seeking government authorization.
Request more information:
Your message has been sent. We will contact you shortly.
From January to June 2019, 52 environmental impact studies were presented to carry out works on electricity networks and build power generation plants in different areas of Central American countries.
The interactive platform "Construction in Central America", compiled by the Business Intelligence Unit at CentralAmericaData, includes an up to date list of public and private construction projects for which environmental impact studies (EIA) were submitted to the respective institutions of each country.
In the first three months of 2019, 14 environmental impact studies were presented in the countries of the region to perform work on electricity grids and develop power generation plants.
The interactive platform "Construction in Central America", compiled by the Trade Intelligence Unit at CentralAmericaData, includes an up to date list of public and private construction projects for which environmental impact studies (EIA) were submitted to the respective institutions of each country.
During 2018, 39 environmental impact studies were presented in the countries of the region to build energy generating plants and work on electricity grids, projects estimated at $455 million.
The interactive platform "Construction in Central America", compiled by the Trade Intelligence Unit at CentralAmericaData, includes an up to date list of public and private construction projects for which environmental impact studies (EIA) were submitted to the respective institutions of each country.
Last year, 87 environmental impact studies were submitted in the countries in the region, for the construction of power generation plants and works on electricity networks.
Panama is the country in the region where the largest investment is concentrated, with an approximate $1.29 billion in energy projects, corresponding to 32 environmental impact studies submitted to the Ministry of the Environment between January and December 2017.
×