Barriers to Opening up the Cell Phone Market

The telephone operators Claro and Movistar are still facing serious bureaucratic obstacles with the municipalities of Costa Rica over the installation of cellular towers.

Thursday, May 24, 2012

Some municipalities are delaying, hindering or even prohibiting the installation of infrastructure by the operators Claro and Movistar, an operation which needs to be carried out in order to comply with their contracts.

The situation has led to the operators requesting an extension of the end of the first phase of infrastructure deployment, whose deadline is July 14, said Eduardo Castellón, a spokesman for the Telecommunications Superintendence (Sutel). This request is being analyzed by the authorities, confirmed Hannia Vega, Deputy Minister of Telecommunications, reports Nacion.com.

In the first phase, 29 cantons should have all the infrastructure deployed.

"It is expected that by the end of May (the requests) will be processesd and recommendations made to the Executive Branch," said Vega.

¿Busca soluciones de inteligencia comercial para su empresa?



More on this topic

Results of the Cell Privatization in Costa Rica

November 2012

After one year of competition in mobile communications, the changes that have taken place reveal a market that is different from how many expected.

The market transformation has been swift and contained surprising nuances. Cellular penetration swiftly exceeded 100%, while the use of mobile Internet exceeded forecasts.

The Monopoly on Cell Phones is Hard to Crack ...

September 2011

Since November 2010 installing a cell phone tower within 15 kilometers of a Costa Rican airport has required a detailed analysis and authorisation by the Civil Aviation Authority.

Prior to that date, the Instituto Costarricense de Electricidad (ICE) had no trouble installing the towers, but now the Directorate General of Civil Aviation (DGCA) has decided to adhere to international standards and make everyone endure the the red tape required for granting installation permits.

Telefónica Prepares Infrastructure for Opening in Costa Rica

June 2011

The Spanish company plans to use third party infrastructure to accelerate its entry into the market.


Mercedes Agüero journalist for La Nacion newspaper interviewed the highest ranking representative of the company in the country.

"There some issues such as base stations and microwave frequencies that are priorities. How could this affect the speed with which they want to deploy the network?

Costa Rica: No Date for Mobile Telephony Auction

March 2010

The process to publish the bidding rules for auctioning several frequencies of the radio spectrum to mobile phone operators is on hold since February.

Sutel, the country’s telecommunication superintendence, explained they are waiting for the government to send the National Frequency Distribution Plan (which modifies the definition of microwave frequencies).