Energy: Contract Renegotiation Prepared

In Costa Rica, the state-owned electricity company ICE is evaluating the renegotiation of prices and conditions in power purchase contracts with private generation companies.

Monday, March 4, 2019

The adjustments planned by the Costa Rican Electricity Institute (ICE) in contracts with private generators are based on the need to reduce costs and adapt prices and quantities purchased to current demand conditions and the availability of resources to generate energy.

See: "$225 Million Investment in Energy Projects"

"... Without detailing specific names of companies, Irene Cañas, executive president of the entity, explained to Nacion.com that "... the space to review the conditions arises with the expiration in June of a contract for a water plant of installed capacity of 14 megawatts (MW). Subsequently, in the last quarter of the year also expires a contract with a wind project of 17 MW."

You may be interested in "Clean Energy: Growing Business in the Region"

"... Now, the revision for expiration of contracts does not worry Mario Alvarado, director of the Costa Rican Association of Energy Producers (Acope). We have lived it before. It is important to show the best goodwill and that the proposal is a winner for all parties as expressed by Irene Cañas herself," he said."

"... However, he warned that changes in certain contractual conditions could have an impact on financial viability, "and therefore it will have to be determined whether the price defined by the Public Services Regulatory Authority (Aresep) adequately incorporates the effects of such modifications through methodology and tariff calculation."

¿Busca soluciones de inteligencia comercial para su empresa?

Do you need more information about your business sector?

Request more information:









this site is protected by reCAPTCHA and Google's privacy policy and terms of service.
Need assistance? Contact us
(506) 4001-6423


More on this topic

650 MW Hydro Project Cancelled

November 2018

After spending $146 million over six years, Costa Rica's state-owned electricity company finally decided to cancel construction of the Diquis hydroelectric power plant in Puntarenas.

Authorities of the Costa Rican Electricity Institute (ICE), informed that decided to cancel the hydroelectric project due to the fall in national energy consumption and because the country has sufficient installed electricity capacity to meet demand in coming years.

Wind Power: More Supply than Needed

April 2016

In Costa Rica, 19 projects were selected as "eligible" by the state run power company, but the same institution has ruled out opening new competitions to purchase more wind-generated power.

EDITORIAL

Investment in alternative energy is risky, because it depends on uncontrollable external factors such as unpredictable weather variations, which have particular effects on hydraulics, solar and wind power.

Costa Rica Does Not Want Private Power Companies

December 2014

Keeping limits on private power generation blocks investments and removes the possibility of reducing prices and improving competitiveness.

According to the Costa Rican government authorities, the country's electricity demand is covered until 2019, an argument which has been used to rule out the draft Contingency Power Act, which proposed increasing private power generation in the country.

NO to Limits on Private Power Generation

October 2014

The Ministry of Environment in Costa Rica is considering raising the ceiling on the amount of energy private generators are allowed to produce above the current 15%, but these companies are demanding the elimination of the ceiling and free competition.

Private power generation companies are opposed to pricing and limits that are imposed on the participation and sale of power in the country, and consider it a "discriminatory act".